All Panels UP





Today I finished installing all 24 panels. I started at nine am and finished at seven am. The second half of the installation went much faster than the first in that I had figured out how to avoid some errors that had to be corrected.
To do: Hang the 150 pound Sunny Boy invertor on the mounting bracket. Install the dc strings in the Sunny Boy. Install the wiring from the Sunny Boy to the AC cut off switch. Get an inspection from the parish electrical inspector. Contact Entergy for grid tie approval and their insertion of the meter.